2018

• In winter, as gas consumption increases due to cold temperatures, the terminal approaches 100% of its rated capacity; on March 1, 27.5 million cubic meters of gas are supplied, which is the highest daily send-out in Adriatic LNG’s history. At the end of the year, annual gas send-out into the national gas pipeline network exceeds 6.5 billion cubic meters. 

• In November, the first LNG cargo from Angola arrives at the terminal. 

 

Operational results  
Carriers offloaded 77
Gas cm sent out into the national grid 6.5 billion
Terminal utilization rate 81%
Reliability rate 99.6%